Deakins Place
9 June 2021Moorways Swimming Pool
3 September 2021Project Details
Area – 2750m2
U Value – 0.15 w/m2k
Linroc Elite Hybrid – Tapered HP EPS150E / foil faced PIR
1:60 Fall
Location: Leicester
The Challenge
Our team were tasked with designing and supplying a tapered scheme for this complex £168 million pound shopping centre development.
The Solution
Working closely with the Architect, Client and the roofing contractor, the team were able to successfully provide a tapered option that met all the requirements including the project’s thermal needs and efficient drainage. The Linroc Elite hybrid system incorporating both PIR and EPS was selected due to its versatility and commercial benefits.
Given the complex geometry of the roofs close collaboration with the design team allowed us to provide a scheme which was simple for the roofing contractor to install, ensuring the system would perform at it’s optimum for years to come.
As with all large projects programme was key, our team here at Linroc liaised perfectly with the site team to ensure the strict delivery schedule was met fully, allowing the site team to meet the programme.
The Outcome
The project was completed on-time and on-budget and due to the close collaboration through the entire process the roof performed as specified and will do for years to come!